路沿石从材质上可分为:水泥混凝土预制、天然石材凿制、砌块砌制及水泥混凝土就地浇筑等;从形式上可分为:直线型和弧线型,其中弧线型主要用于道路曲线段和路口处。
The material of curbstone can be divided into: cement concrete
prefabrication, natural stone chiseling, block masonry and cement
concrete pouring in place, etc.; in form, it can be divided into:
straight line type and arc type, in which arc type is mainly used for
curved road sections and intersections.
在直线段,可以在核对道路中心线无误后,直接依次丈量出路面边界,进行路边线放样,同时也可以采用全站仪测设,在定出边桩以控制方向和高程后,直线段的边桩与边桩间可拉线作为准绳,桩距为
10m~15m,在相邻间隔10m~15m的路沿石顶面拉根线绳(注意绷紧线绳),据此,再将空缺路沿石表面摆顺畅。曲线弯道以及交叉口路段均按设计半径加密边桩
检查井钢模具 隔离墩模具 隔离墩钢模具 流水槽模具 U型槽模具 螺杆启闭机 卷扬式启闭机 铜雕佛像 ,桩距为5m~10m,路口桩距为1m~5m,保证曲线圆弧尺寸。曲线一般可以用全站仪测设,保证精准性。
In the straight line section, after checking the center line of the
road, directly measure the road boundary in turn, set out the roadside
line, and at the same time, use the total station to measure the setting
out. After setting out the side pile to control the direction and
elevation, the line between the side pile and the side pile in the
straight line section can be used as the reference line. The distance
between the piles is 10m-15m, and the line is pulled along the top of
the stone at the adjacent interval of 10m-15m (pay attention to
tightening the line According to this, the vacant road shall be placed
smoothly along the stone surface. The side piles shall be densified
according to the design radius for curve curves and intersections. The
pile spacing shall be 5m-10m, and the pile spacing at intersections
shall be 1m-5m to ensure the curve arc size. Generally, the curve can be
measured with total station to ensure the accurac